Agenda

1. Roll Call

Attachments (27)

2. Welcome to the Region

Attachments (1)

3. Approval of Minutes for August 20-21, 2026

Attachments (92)

4. Commissioner Meetings for Compensation

Attachments (1)

5. Committee Member Compensation

Attachments (1)

6. Commission Chief Deputy Director

Attachments (94)

7. Commissioner and Ex-Officio Reports

Attachments (1)

8. CalSTA Undersecretary

Attachments (2)

9. Caltrans Director

Attachments (1)

10. FHWA California Division Administrator

Attachments (2)

11. Regional Agencies Moderator

Attachments (1)

12. Rural Counties Task Force Chair

Attachments (1)

13. Self-Help Counties Coalition Executive Director

Attachments (1)

14. Equity Initiatives Update • Equity Advisory Committee Update

Attachments (40)

15. State and Federal Legislative Matters

Attachments (1)

16. Budget and Allocation Capacity

Attachments (2)

17. Innovations in Transportation • Artificial Intelligence Cameras in Caltrans District 5

Attachments (3)

18. Draft Toll Facility Application Guidelines

Attachments (1)

19. 2026 Local Streets and Roads Needs Assessment

Attachments (1)

20. Delegated Authority to Allocate Funds to Respond to Emergencies Resolution G-26-74

Attachments (6)

21. Adoption of the FY 2026-27 Road Maintenance and Rehabilitation Account Local Streets and Roads Funding Subsequent Report of Eligible Cities Resolution G-26-71

Attachments (4)

22. 2026 Status Report for the Active Transportation Program

Attachments (2)

23. Fourth Quarter – Project Delivery Report – Fiscal Year 2025-26

Attachments (4)

24. Informational Reports on Allocations Under Delegated Authority -- Emergency G-11 Allocations (2.5f.(1)): $28,455,000 for 14 projects. -- SHOPP Safety Sub allocations (2.5f.(3)): $62,963,000 for six projects. -- Minor G-19-05a Allocations (2.5f.(4)): $4,719,000 for four projects.

Attachments (20)

25. STIP Amendment for Notice: 2 The Tulare County Association of Governments (TCAG) proposes to amend the 2026 STIP to program an Assembly Bill (AB) 3090 Reimbursement Project (PPNO 8113A) to advance the Project Approval and Environmental Document (PA&ED) phase of the State Route 198 and Road 148 Interchange, Safety, and Multi-Modal Project (PPNO 8113) from Fiscal Year 2028-29 to 2026-27 using local Measure R funds. Reimbursement would be scheduled over a 2-year period beginning in 2028-29. STIP Amendment 26S-13

Attachments (11)

26. STIP Amendment for Notice: 2 The City of Los Angeles proposes to amend the 2026 STIP to deprogram $15,082,000 in STIP (RIP) funds from Fiscal Year 2027-28 for the Soto Street Roadway Widening between Multnomah Street and Mission Road project (PPNO 5961), and program these funds to the new proposed Huntington Drive Multi-Modal Transportation Improvement Project, Segments 1 and 2 (PPNO 6645), for the PS&E and Construction Capital (CON Cap) phases, in Los Angeles County. STIP Amendment 26S-14

Attachments (7)

27. State Highway Projects, per Resolution G-06-08

Attachments (2)

28. Local Assistance STIP Projects, per Resolution G-13-07

Attachments (1)

29. Local Assistance ATP Projects, per Resolution G-15-04

Attachments (1)

30. Pre-Construction SHOPP Support Allocations, per Resolution G-06-08

Attachments (1)

31. Status of Allocation for SHOPP Projects

Attachments (1)

32. Fiscal Year 2025-26 Caltrans Finance Report

Attachments (1)

33. Report on Fiscal Year 2025-26 Right of Way Annual Allocation

Attachments (2)

34. Aeronautics – Acquisition and Development and Airport Improvement Program

Attachments (2)

35. Quarterly Report – Local Assistance Annual Allocation for the Period Ending June 30, 2026

Attachments (2)

36. Fiscal Year 2025-26 – Fourth Quarter – Airspace Program Report

Attachments (2)

37. Update on the Minor B project list under the 2026-27 SHOPP Minor Construction Program

Attachments (2)

38. Proposition 1B Semi-Annual Report

Attachments (1)

39. Third Quarter – Balance Report on AB 1012 “Use It or Lose It” Provision for Federal Fiscal Year 2024 Unobligated RSTP and CMAQ Funds

Attachments (6)

40. Proposition 1A High-Speed Passenger Train Bond Program – Semi-Annual Report for Fiscal Year 2025-26

Attachments (2)

41. Fiscal Year 2025-26 Senate Bill 1 Semi-Annual Report

Attachments (1)

42. Final Close-Out Report on the 2025-26 Minor Program Annual Allocation

Attachments (1)

43. Fiscal Year 2025-26 Local Transportation Climate Adaptation Program Semi-Annual Report

Attachments (2)

44. Transit and Intercity Rail Capital Program (TIRCP) – Program Update

Attachments (2)

45. State Transportation Improvement Program (STIP) 2 Amendment for Action: The San Diego Association of Governments proposes to amend the 2026 STIP to deprogram $62,000,000 in STIP (IIP) funds programmed in Fiscal Year 2028-29 and delete the project from the 2026 STIP to advance construction of the San Dieguito Bridge Replacement, Double Track and Special Events Platform Project (San Dieguito Phase 2) (PPNO CP119) in San Diego County using alternative funding sources. STIP Amendment 26S-11

Attachments (3)

46. STIP Amendment for Action: 2 The Department, Contra Costa Transportation Authority (CCTA), and the Metropolitan Transportation Commission (MTC) propose to amend the 2026 STIP to deprogram $7,500,000 in STIP (RIP) funds currently programmed to the Plans, Specifications, and Estimate (PS&E) phase of the SR4 Operational Improvements – Phase 1 project (0299A) and program these funds to the Construction phase of the I-80/San Pablo Dam Interchange-Phase 2 project (PPNO 0242K) in Contra Costa County, in Fiscal Year 2028-29. STIP Amendment 26S-12

Attachments (6)

47. Approval of Project for Future Consideration of Funding: 2 03-Sacramento County Alta Arden Expressway Phase I Provide sidewalks, bicycle lanes, rehabilitation, and resurfacing. (MND) (PPNO 1923) (STIP) Resolution E-26-74 (Related Item under Ref.: 2.5c.(3))

Attachments (7)

48. Approval of Project for Future Consideration of Funding: 2 03-Sacramento County Laguna Creek Inter-Regional Trail Crossing over State Route 99 Provide a pedestrian overcrossing and multi-use trail. (MND) (PPNO 5402) (ATP) Resolution E-26-75 (Related Item under Ref.: 2.5w.(2))

Attachments (4)

49. Approval of Project for Future Consideration of Funding: 2 03-Sacramento County Zinfandel Drive Bicycle and Pedestrian Overcrossing Provide a bicycle and pedestrian overcrossing and Class 1 path. (MND) (PPNO 5406) (ATP) Resolution E-26-76

Attachments (2)

50. Approval of Five Projects for Future Consideration of 2 Funding: 01-03-Sie-89, PM 0.0/15.2 Henness Pass CAPM Project The project will preserve and extend the life of existing pavement on State Route 89, rehabilitate or replace culverts, upgrade metal beam guardrail, replace an existing census station, and construct a maintenance vehicle pullout on State Route 89 in Sierra County, between Post Miles 0.0 to 15.2, south of Sierraville. (MND) (PPNO 8028) (SHOPP) Resolution E-26-77 (Related Item under Ref.: 2.5b.(2)) 02-04-Sol-12, PM 14.10/20.68 Solano State Route 12 Pavement Preservation Perform pavement preservation including pavement dig- outs, cold planing, and asphalt concrete overlay and dikes; installing centerline and shoulder (edgeline) rumble strips; shoulder widening; and constructing drainage improvements. The proposed project will also upgrade metal beam guardrail, upgrade traffic signing panels, and delineate pavement. (MND) (PPNO 2921D) (SHOPP) Resolution E-26-68 (Related Item under Ref.: 2.5b.(2)) 03-05-SLO-166, PM 8.9/16.0 State Route 166 Capital Preventive Maintenance Project Preserve 14.2 lane miles of Class III pavement, restore three drainage systems, and upgrade five guardrail locations to Manual for Assessing Safety Hardware standards. (MND) (PPNO 3071) (SHOPP) Resolution E-26-69 (Related Item under Ref.: 2.5b.(2)) 04-08-Riv-371, PM 67.1/67.4 SR-371 Install Left Turn Lane Project Construct left turn lane in the westbound direction of State Route 371 at the Homestead Road intersection. The proposed project will also include constructing a Modified Concrete Barrier in the eastbound direction of State Route 371, construction of cut slopes and embankment slopes, and minor grading work. (MND) (PPNO 3021J) (SHOPP) Resolution E-26-71 (Related Item under Ref.: 2.5b.(2)) 05-08-SBd-38, PM 7.0/46.6 SR-38 Upgrade Guardrail End Treatments, Culverts, and Correct Grading Project Correct grading and upgrade end treatments of existing guardrail and culverts along State Route 38 from Post Mile 7.0 to 46.6 in San Bernardino County, California. (MND) (PPNO 3014V) (SHOPP) Resolution E-26-72 (Related Item under Ref.: 2.5b.(2))

Attachments (18)

51. Approval of Project for Future Consideration of Funding: 2 07-LA-71, PM R0.5/R4.7 08-SBd-71, PM R0.0/R0.2 State Route 71 Freeway Upgrade and Interchange Improvement Project This project involves upgrading State Route 71 from a combination of 4-lane expressway and 6-lane freeway into an 8-lane freeway, with 3 mixed-flow lanes and 1 High Occupancy Vehicle (HOV) lane in each direction between Interstate 10 and the Los Angeles/San Bernardino County line in both counties. This will be achieved by widening or restriping to add either one or two lanes depending on the location. Additional improvements include replacing two railroad overhead bridges with raised profiles to meet current vertical clearance standards, replacing an existing pedestrian overcrossing, and eliminating local crossings between Mission Boulevard (Blvd) and Rio Rancho Road. The project will also repave the roadway, reconstruct on- and off-ramps at Valley and Mission Blvd, as well as the southbound Rio Rancho Road off-ramp. In addition, paving and striping 0.2 miles into San Bernardino County to maintain HOV lane continuity. Furthermore, the project includes constructing soundwalls and retaining walls, installing Permanent Best Management Practices, and shifting the centerline alignment westward from Mission Blvd to Old Pomona Road to minimize right of way impacts. (MND Addenda) (PPNO 2741) (STIP) Resolution E-26-73A 05-SLO-101-PM 61.7/62.2 Right of way along United States Highway 101 on San Paso Circle and Wellsona Road, in the county of San Luis Obispo Resolution R-4130

Attachments (6)

54. Director’s Deeds Items 1 through 10 Excess Lands - Return to State: $1,366,000

Attachments (5)

55. Director’s Deeds Items 1 through 10 Highway 50 Soundwall Excess Lands - Return to State $0 Successor Trustee of the Thomas P. Altenreuther 2018 Revocable Trust Under Instrument Dated June 6, 2018 Separate Property 04-Son-116-PM 39.3 EA 2Q7709

Attachments (7)

57. State Highway Operation and Protection Program 2 (SHOPP) – Allocation Amendment Request to amend the SHOPP Commercial Vehicle Enforcement Facilities project, in Los Angeles County, to rescind the full amount of $572,000 from the PA&ED phase due to the request being inadvertently submitted at the June 2026 Commission meeting. (PPNO 6244) Resolution FP-26-21, Amending Resolution FP-25-107

Attachments (5)

58. STIP – Allocation Amendment Request to amend the State-Administered STIP Feather River Inn Intersection Improvement project, on the State Highway System, in Plumas County, to include the original request to extend the period of project completion an additional 6 months beyond the 36-month Timely Use of Funds deadline, due to an administrative error. There is no change to the allocation amount. (PPNO 3703) Resolution FP-26-22, Amending Resolution FP-22-47 (Related Items under Ref.: 2.8c.(1) and 2.8c.(3))

Attachments (6)

59. STIP – Allocation Amendment Request to amend the State-Administered STIP SR 99/120 Connector Project Phase 1B, on the State Highway System, in San Joaquin County, to move $1,200,000 from Right of Way (RW) Capital to RW Support. There is no change to the allocation amount. (PPNO 3162B) Resolution FP-26-23, Amending Resolution FP-25-113

Attachments (3)

60. Multi–funded STIP, Local Partnership Program (LPP) (Formulaic), Trade Corridor Enhancement Program (TCEP), and Proposition 1B Trade Corridor Improvement Fund (TCIF) – Allocation Amendment Request to amend the locally-administered multi-funded STIP, LPP (Formulaic), TCEP, and Proposition 1B TCIF I-10 Corridor Express Lanes Contract 1 project, on the State Highway System, in San Bernardino County, to split the original Proposition 1B TCIF allocation between two Budget Authority fiscal years. There is no change to the allocation amount. (PPNO 3009P) Resolution FP-26-25, Amending Resolution FP-17-77 Resolution LPP-A-2627-06, Amending Resolution LPP-A-1718-13 Resolution TCEP-A-2627-06, Amending Resolution TCEP-A-1718-05 Resolution TCIF-AA-2627-13, Amending Resolution TCIF-A-1718-04

Attachments (3)

61. TCEP – Allocation Amendment Request to amend the State-Administered TCEP Yolo 80 Corridor Improvements Project - Phase 1, on the State Highway System, in Yolo County, to correct the State and Regional splits for the Construction, Construction Support, and Right of Way Support phases for the TCEP-State and TCEP-Regional funding amounts. There is no change to the allocation amount. (PPNO 8922A) Resolution TCEP-A-2627-07, Amending Resolution TCEP-A-2324-17

Attachments (5)

62. TCEP – Allocation Amendment Request to amend the locally-administered TCEP Green Power Microgrid – Harbor Facilities Component project, off the State Highway System, in Alameda County, to deallocate $3,632,000 from the Construction (CON) phase due to a program amendment approved by the Commission in June 2026. (PPNO 2090S) Resolution TCEP-A-2627-09, Amending Resolution TCEP-A-2425-25 (Related Item under Ref.: 4.9)

Attachments (2)

63. TCEP – Allocation Amendment Request to amend the locally-administered TCEP Route 605/91 Interchange Improvement: Gateway Cities Freight Crossroads Project, on the State Highway System, in Los Angeles County, to deallocate $69,670,000 from the CON phase due to lapsed access to funds. (PPNO 5388) Resolution TCEP-A-2627-10, Amending Resolution TCEP-A-2324-26

Attachments (5)

64. Solutions for Congested Corridors Program (SCCP) – Allocation Amendment Request to amend the locally-administered SCCP Dry Creek Greenway Multi-Use Trail Project, off the State Highway System, in Placer County, to revise the PPNO from 1526 to 1526A, and the ATP allocation note, and add the combined project note. There is no change to the allocation amount. Resolution SCCP-A-2627-01, Amending Resolution SCCP-A-2223-09 (Related Item under Ref.: 2.5w.(6))

Attachments (4)

65. Active Transportation Program (ATP) – Allocation Amendment Request to amend the locally-administered ATP Dry Creek Greenway Multi-Use Trail Project, off the State Highway System, in Placer County, to add the combined project note and infrastructure note. There is no change to the allocation amount. (PPNO 1526A) Resolution FATP-2627-06, Amending Resolution FATP-2223-23 (Related Item under Ref.: 2.5s.(15))

Attachments (3)

66. Multi–Funded Transit & Intercity Rail Capital Program (TIRCP) and Proposition 1B Intercity Rail (ICR) – Allocation Amendment Request to amend the multi–funded TIRCP and Proposition 1B ICR (2018:12) Building Up: LOSSAN North Improvement Program (Canada Honda Bridge Replacement) component, in Santa Barbara County, to deallocate $49,000 from the CON phase to reflect component savings. (PPNO CP042B) Resolution TIRCP-2627-19S, Amending Resolution TIRCP-2425-43S Resolution ICR1B-AA-2627-01S, Amending Resolution ICR1B-A-2425-02S

Attachments (4)

67. TIRCP – Allocation Amendment Request to amend the TIRCP (2020:16) Improving Air Quality and the Economic Growth with Electric Buses in Merced County, the Gateway to Yosemite (Procurement of 3 Zero-Emission Buses) component, to deallocate $478,000 from the CON phase to reflect component savings. (PPNO CP074) Resolution TIRCP-2627-20, Amending Resolution TIRCP-2021-06

Attachments (8)

68. TIRCP – Allocation Amendment Request to amend the TIRCP (2020:04) Inglewood Transit Connector Project (Design for Inglewood Transit Connector Project Phase 1) component, in Los Angeles County, to revise the project description. There is no change to the allocation amount. (PPNO CP062D) Resolution TIRCP-2627-21, Amending Resolution TIRCP-2425-63

Attachments (1)

69. TIRCP – Allocation Amendment Request to amend the TIRCP (2022:21) Sonoma Regional Bus and Rail Connectivity Improvements (Real-Time Sign Installation) component, in Sonoma County, to rescind the full amount of $50,000 from the CON phase due to the lack of infrastructure services. (PPNO CP100S) Resolution TIRCP-2627-22, Amending Resolution TIRCP-2526-47 (Related Item under Ref.: 2.6g.(1))

Attachments (2)

70. TIRCP – Allocation Amendment Request to amend the TIRCP (2018:27) Southern California Optimization Rail Expansion (SCORE) (Link US - West Bank Tie-in 1) component, in Los Angeles County, to rescind the full amount of $54,385,000 from the CON phase due to an update to the delivery contract. (PPNO CP033) Resolution TIRCP-2627-23, Amending Resolution TIRCP-2526-47

Attachments (3)

71. TIRCP – Allocation Amendment Request to amend the TIRCP (2018:26) SMART Larkspur to Windsor Corridor (Windsor to Healdsburg North Extension) component, in Sonoma County, to deallocate $800,000 from the PS&E phase to reflect component savings. (PPNO CP041B) Resolution TIRCP-2627-24, Amending Resolution TIRCP-2526-45 (Related Items under Ref.: 2.6g.(2) and 2.6s.(8))

Attachments (1)

72. TIRCP – Allocation Amendment Request to amend TIRCP (2022:01) ATN FAST (Family of Advanced Solutions for Transit): Revolutionizing Transit for a Global Audience project, in Orange County, to rescind a combined total of $14,574,000 from the CON phase of four components due to project termination. • $877,000 from the Purchase 7 ZEV vans for EVE: New Airport Connection & Night Owl) component. (PPNO CP086) (2.6g.(10a)) Resolution TIRCP-2627-25, Amending Resolution TIRCP-2425-74 • $313,000 from the Purchase of 10 (5 passenger) ZEV Microtransit for FRAN component. (PPNO CP086A) (2.6g.(10b)) Resolution TIRCP-2627-26, Amending Resolution TIRCP-2425-74 • $12,836,000 from the Purchase of 15 - 40' Zero Emission Buses for ART Fleet Conversion component. (PPNO CP086C) (2.6g.(10c)) Resolution TIRCP 2627-27, Amending Resolution TIRCP-2425-74 • $548,000 from the Capital Outlay ANNA Corridor component. (PPNO CP086D) (2.6g.(10d)) Resolution TIRCP-2627-28, Amending Resolution TIRCP-2223-82

Attachments (12)

73. Approval of Two 2022 Trade Corridor Enhancement Program Baseline Agreement Amendments Resolution TCEP-P-2627-01BA, Amending Resolutions TCEP-P-2425-01BA and TCEP-P-2324-07B (Related Item under Ref.: 2.5s.(13))

Attachments (3)

74. Approval of the 2024 Baseline Agreement Amendment for the Forum Mobility – Beyond the Dock: Heavy-Duty Electrification of the Port of Oakland Priority Trade Corridors Project Resolution TCEP-P-2627-02BA, Amending Resolution TCEP-P-2526-08B

Attachments (2)

75. Approval of 2023 Active Transportation Program Baseline Agreement for the Harden Parkway Safe Routes to School project. Resolution ATP-P-2627-03B (Related Item under Ref.: 2.5w.(1))

Attachments (2)

76. Approval of two State Highway Operation and Protection Program Baseline Agreements Resolution SHOPP-P-2627-02B

Attachments (2)

77. Approval of Report on the Status of the Transit and Intercity Rail Capital Program Loan (Assembly Bill 117)

Attachments (3)

78. Airspace Lease Program Update

Attachments (1)

79. Airspace Lease – Request to Directly Negotiate Items 1 through 8

Attachments (2)

80. Director’s Deed Item 1 Roberti Fair Market Value Buyer Excess Lands - Return $765,000 to State Route 710 Rehabilitation Account

Attachments (3)

81. Request for an additional $5,447,000 (16.8 percent 2. increase) in Pre-Construction Right of Way (RW) Capital, for the TCEP Tulare SR 99 Corridor and Paige Avenue Multimodal Interchange Enhancements project on State Route 99, in Tulare County. (EA 48950, PPNO 6369) Resolution TCEP-A-2627-11S

Attachments (5)

82. Request for an additional $300,000 (14.1 percent 2. increase) in Pre-Construction Support for the PA&ED phase, for the SHOPP Bridge Rehabilitation and Replacement project on State Route 96, in Siskiyou County. (EA 0H730, PPNO 3660) Resolution FA-26-07

Attachments (3)

83. Request for an additional $1,200,000 (9.0 percent 2 increase) in Construction Support for the SHOPP Bridge Rehabilitation and Replacement project on United States Highway 101, in Del Norte County. (EA 43640, PPNO 0100V) Resolution FA-26-08 (Related Item under Ref.: 2.8v.(3))

Attachments (4)

84. Request for an additional $2,800,000 (32.9 percent 2 increase) in Construction Support for the SHOPP Bridge Formula Program project on State Route 20 and Interstate 80, in Nevada and Placer counties. (EA 3H560, PPNO 4305) Resolution FA-26-09

Attachments (3)

85. Request for an additional $750,000 (33.4 percent 2 increase) in Construction Support, for the SHOPP Safety Improvements project on State Route 9, in Santa Cruz County. (EA 1M400, PPNO 3012) Resolution FA-26-10

Attachments (3)

86. Request for an additional $3,574,000 (14.7 percent 2 increase) in Construction Capital and $1,189,000 (30.6 percent increase) in Construction Support, for the SHOPP Roadway Rehabilitation project on State Route 216, in Tulare County. (EA 0W90U, PPNO 8039) Resolution FA-26-11

Attachments (3)

87. Request for an additional $1,700,000 (23.3 percent 2 increase) in Construction Capital for the SHOPP Americans with Disabilities Act Curb Ramps project on State Route 116, in Sonoma County. (EA 4J460, PPNO 1491B) Resolution FA-26-12

Attachments (3)

88. Request for an additional $800,000 (55 percent 2 increase) for the PS&E phase of the TIRCP (2018:26) SMART Larkspur to Windsor Corridor (Windsor to Healdsburg) component, in Sonoma County. (PPNO CP041A) Resolution TIRCP-2627-29S (Related Items under Ref.: 2.6g.(9) and 2.6s.(8))

Attachments (4)

89. SHOPP Amendments for Approval: 2 Request to: --Add 22 new projects into the 2026 SHOPP. (2.1a.(1a) and 2.1a.(1b)) --Revise 16 projects currently programmed in the 2026 SHOPP. (2.1a.(1d)) SHOPP Amendment 26H-004 (Related Items under Ref.: 2.5b.(1) and 2.5b.(2))

Attachments (7)

90. Director’s Orders Annual Close-out Report for Fiscal Year 2025-26

Attachments (1)

91. 2024 Trade Corridor Enhancement Program Amendment Amendments to the Coastal Rail Infrastructure Resiliency Project and the Pennsylvania Avenue Grade Separation Project Resolution G-26-73, Amending Resolution G-26-57 (Related Item under Ref.: 2.6s.(9))

Attachments (2)

92. Local Partnership Formulaic Program Amendment Add the Downtown Pedestrian and Bicycle Crossing of US 101 project in Sonoma County and program $1,117,000. Resolution LPP-P-2627-03, Amending Resolution LPP-P-2627-01

Attachments (2)

93. Local Assistance (Federal) – Annual Allocation Request of $2,739,885,000 in Federal Funds for Local Assistance Annual Allocation for Fiscal Year 2026–27. Resolution FM-26-01

Attachments (3)

94. Request of $120,294,000 for 10 SHOPP projects. 2 Resolution FP-26-26 (Related Item under Ref.: 2.1a.(1))

Attachments (4)

95. Request of $47,035,000 for 35 2026 SHOPP 2 preconstruction project phases for environmental support, design, and RW support. Resolution FP-26-27 (Related Items under Ref.: 2.1a.(1) and 2.2c.(1))

Attachments (5)

96. Request of $300,000 for the locally-administered STIP 2 SR 49 San Andreas Southern Gateway Improvements Project, on the State Highway System, in Calaveras County. (PPNO 3724) Resolution FP-26-28

Attachments (3)

97. Request of $4,993,000 for seven locally-administered 2 STIP and Planning, programming, and Monitoring projects off the State Highway System. Resolution FP-26-29 (Related Item under Ref.: 2.2c.(3))

Attachments (5)

98. Request of $123,000 for the locally-administered LPP 2 (Formulaic) Aten Boulevard Rehabilitation Project between Old State Route 86 and the West Right-of-Way Line of the Southern Pacific Railroad, off the State Highway System, in Imperial County. (PPNO 1618) Resolution LPP-A-2627-07

Attachments (4)

99. Request of $162,207,000 for the locally-administered 2 multi-funded SCCP, LPP (Competitive and Formulaic), and TIRCP Sonoma-Marin Area Rail Transit District (SMART) Healdsburg Extension Project, in Sonoma County. (PPNO 2364N) Resolution SCCP-A-2627-02 Resolution LPP-A-2627-08 Resolution TIRCP-2627-30 (Related Items under Ref.: 2.6g.(2) and 2.6g.(9))

Attachments (3)

100. Request of $64,257,000 for the multi-funded TCEP and 2 TIRCP (2024:16) Coastal Rail Infrastructure Resiliency Project (Sand Replenishment), in Orange County. (PPNO CP171E) Resolution TCEP-A-2627-15 Resolution TIRCP-2627-32 (Related Item under Ref.: 4.15)

Attachments (5)

101. Request of $15,084,000 for the locally-administered 2 multi-funded TCEP and STIP Hueneme Road Widening - Edison Drive to Rice Avenue project, off the State Highway System, in Ventura County. (PPNO 6464) Resolution TCEP-A-2627-12 Resolution FP-26-30

Attachments (4)

102. Request of $3,653,000 for the locally-administered TCEP 2 Long Beach-East Los Angeles Corridor Zero-Emissions Truck Project (MN8 Energy), off the State Highway System, in Los Angeles County. (PPNO Z004B) Resolution TCEP-A-2627-13

Attachments (2)

103. Request of $7,900,000 for the State-Administered TCEP 2.5 EV Realty - South Bay Truck Charging Hub project, off the State Highway System, in Los Angeles County. (PPNO Z003) Resolution TCEP-A-2627-16

Attachments (2)

104. Request of $16,029,000 for nine locally-administered 2. ATP projects, off the State Highway System. Resolution FATP-2627-07 (Related Items under Ref.: 2.8v.(6) and 4.11)

Attachments (4)

105. Request of $6,874,000 for the locally-administered ATP 2. Laguna Creek Inter-Regional Trail Crossing at State Route 99 project, on the State Highway System, in Sacramento County. (PPNO 5402) Resolution FATP-2627-08 (Related Item under Ref.: 2.2c.(4))

Attachments (4)

106. Request of $106,625,000 for 11 TIRCP projects. 2 Resolution TIRCP-2627-31 (Related Item under Ref.: 2.6g.(6))

Attachments (5)

107. Request to extend the period of contract award for the 2 SHOPP Safety Improvements project, in San Luis Obispo County, per SHOPP Guidelines. (PPNO 2766Y) Waiver 26-191

Attachments (4)

108. Request to extend the period of project completion for 2 six SHOPP projects, per SHOPP Guidelines. Waiver 26-192 (Related Items under Ref.: 2.5c.(4), 2.8c.(2), and 2.8c.(3))

Attachments (9)

109. Request to extend the period of project development 2 expenditure for six SHOPP projects, per SHOPP Guidelines. Waiver 26-193

Attachments (3)

110. Request to extend the period of contract award for four 2 locally-administered STIP projects, off the State Highway System, per STIP Guidelines. Waiver 26-194

Attachments (3)

111. Request to extend the period of project completion for 2 the State-Administered STIP I-5 North Coast Corridor HOV Extension, Phase 1, Carlsbad Seg, Package 3 (CMGC) project, on the State Highway System, in San Diego County, per STIP Guidelines. (PPNO 0615I) Waiver 26-195 (Related Item under Ref.: 2.8c.(1))

Attachments (2)

112. Request to extend the period of project completion for 2 the State-Administered STIP Feather River Inn Intersection Improvement project, on the State Highway System, in Plumas County, per STIP Guidelines. (PPNO 3703) Waiver 26-196 (Related Items under Ref.: 2.5c.(4) and 2.8c.(1))

Attachments (1)

113. Request to extend the period of project completion for 2 the State-administered multi-funded STIP and LPP (Competitive and Formulaic) US 101 Hearn Avenue Regional Multimodal Interchange project, on the State Highway System, in Sonoma County, per STIP and LPP (Competitive and Formulaic) Guidelines. (PPNO 0785C) Waiver 26-197

Attachments (3)

114. Request to extend the period of contract award for the 2 locally-administered ATP Downtown Long Beach Walkable Corners project, off the State Highway System, in Los Angeles County, per ATP Guidelines. (PPNO 5865A) Waiver 26-198

Attachments (3)

115. Request to extend the period of project completion for 2 four locally-administered ATP projects, off the State Highway System, per ATP Guidelines. Waiver 26-199

Attachments (2)

116. Request to extend the period of contract award for two 2 TIRCP (2024:27) UCLA/Westwood Zero Emission Transit Service Expansion: Deploying Wireless Charging at Scale components, in Los Angeles County, per TIRCP Allocation Policy. Waiver 26-200

Attachments (3)

117. Request to extend the period of project completion for 2 the TIRCP (2020:02) Transbay Corridor Core Capacity Program (Vehicle Acquisition) component, in various counties, per TIRCP Allocation Policy. (PPNO CP060) Waiver 26-201

Attachments (2)

118. Post-Fact request to extend the period of project 2 development expenditure for two phases of the locally- administered ATP La Vina Community Mobility and Safety Enhancements Project, off the State Highway System, in Madera County. (PPNO 8017) Waiver 26-210

Attachments (3)

119. Request to amend the period of project completion for 2 the SHOPP Mobility project, in Ventura County, as an exception to SHOPP Guidelines. (PPNO 5255) Waiver 26-203, Amending Waiver 25-172

Attachments (4)

120. Request to amend the period of project development 2 expenditure for the SHOPP Bridge Preservation project, in Del Norte County, as an exception to the SHOPP Guidelines. (PPNO 0100V) Waiver 26-204, Amending Waiver 23-171 (Related Item under Ref.: 2.5e.(1))

Attachments (3)

121. Request to amend the period of contract award for the 2 SCCP Los Angeles Metro CORE Capacity & System Integration Project (Replacement-TPSS), in Los Angeles County. (PPNO 6210A) Waiver 26-206, Amending Waiver 26-121

Attachments (4)

122. Request to amend the period of project allocation for 2 three locally-administered ATP projects, off the State Highway System. Waiver 26-207, Amending Waivers 25-79 and 25-126 (Related Item under Ref.: 2.5w.(1))

Attachments (4)

123. Request to amend the period of project completion for 2 the locally-administered ATP San Diego Regional Border to Bayshore Bikeway Project, off the State Highway System, in San Diego County. (PPNO 1232) Waiver 26-208, Amending Waiver 25-156 Public Comment

Attachments (243)

Agenda Items

  1. 00:04:09 Airspace Lease Program Update Caltrans reported on lease inventories, overdue rents, safety inspections, and audit corrective actions, with commissioners requesting additional revenue information.
  2. 00:19:27 Airspace Leases: Requests to Directly Negotiate The commission approved direct negotiation of eight airspace leases for temporary construction encroachments and landlocked parcels.
  3. 00:21:39 SR 99 and Paige Avenue Supplemental Right-of-Way Funding The commission approved $5.447 million in additional right-of-way funding for canal relocation costs associated with the Tulare County interchange project.
  4. 00:26:58 SR 96 Bridge Project Supplemental Environmental Support The commission approved $300,000 for additional hydraulic analysis, bridge redesign, and value analysis for the Siskiyou County project.
  5. 00:27:33 US 101 Bridge Project Supplemental Construction Support The commission approved $1.2 million in additional construction support for site conditions, environmental protection, inspections, and delays in Del Norte County.
  6. 00:28:20 SR 20 and I-80 Bridge Project Supplemental Construction Support The commission approved $2.8 million in construction support for bridge reconstruction challenges, railroad constraints, and weather-related delays.
  7. 00:28:59 SR 9 Safety Project Supplemental Construction Support The commission approved $750,000 in construction support for unforeseen utility conflicts and changes to retaining walls, drainage, and traffic control.
  8. 00:29:21 SR 216 Rehabilitation Supplemental Construction Funding The commission approved $3.574 million in construction capital and $1.189 million in support for utility relocations and additional safety and structural work.
  9. 00:30:24 SR 116 ADA Curb Ramps Supplemental Construction Funding The commission approved $1.7 million to close out construction after site conditions, construction sequencing changes, and utility conflicts increased costs.
  10. 00:32:08 SMART Windsor to Healdsburg Supplemental Design Funding The commission approved $800,000 in supplemental design funding for the SMART Windsor to Healdsburg corridor component.
  11. 00:33:11 2026 SHOPP Amendments The commission approved adding 22 projects and revising 16 projects, including reprogramming lapsed projects and adding Caldecott Tunnel control system work.
  12. 00:34:56 Director’s Orders Annual Close-out Report Staff reported approximately $801 million in emergency construction contracts for 191 projects and $248 million in federal emergency relief allocations.
  13. 00:37:09 Trade Corridor Enhancement Program Amendments The commission approved withdrawing the Pennsylvania Avenue grade separation from the 2024 program and splitting coastal rail protection work into separate components.
  14. 00:44:46 Windsor US 101 Pedestrian and Bicycle Crossing Programming The commission approved programming $1.117 million for Windsor’s downtown pedestrian and bicycle crossing improvements.
  15. 00:46:23 Federal Local Assistance Annual Allocation The commission approved $2.739885 billion in federal local assistance funds for fiscal year 2026–27.
  16. 00:47:24 SHOPP Construction Allocations After one project was withdrawn, the commission approved $110.092 million for nine highway improvement projects.
  17. 00:48:03 SHOPP Preconstruction Allocations The commission approved $47.035 million for 35 environmental, design, and right-of-way project phases.
  18. 00:48:55 SR 49 San Andreas Southern Gateway Allocation The commission approved $300,000 for the SR 49 San Andreas Southern Gateway Improvements Project.
  19. 00:49:16 Local STIP and Planning Allocations The commission approved $4.993 million for seven local STIP and planning, programming, and monitoring allocations.
  20. 00:50:22 Aten Boulevard Rehabilitation Allocation The commission approved $123,000 for roadway rehabilitation and thermoplastic striping on Aten Boulevard in Imperial County.
  21. 00:51:29 SMART Healdsburg Extension Allocation The commission approved $162.207 million for the SMART Healdsburg extension and discussed ridership growth, youth access, and bicycle and pedestrian connections.
  22. 00:58:59 Transit and Intercity Rail Capital Program Allocations The commission approved funding for 11 transit and rail projects following Commissioner Mann’s recusal over a potential financial conflict.
  23. 01:00:51 Hueneme Road Widening Allocation The commission approved $15.084 million for design and right-of-way phases of Hueneme Road widening to improve freight access and safety.
  24. 01:01:23 Long Beach–East Los Angeles Zero-Emissions Truck Allocation The commission approved $3.653 million for infrastructure supporting zero-emission heavy-duty trucks along the I-710 freight corridor.
  25. 01:01:53 EV Realty South Bay Truck Charging Hub Allocation The commission approved $7.9 million for a heavy-duty electric truck charging hub in Los Angeles County.
  26. 01:03:09 Local Active Transportation Program Allocations Following the withdrawal of two projects, the commission approved $12.341 million for seven projects improving walking, cycling, and accessibility.
  27. 01:03:53 Laguna Creek Trail Crossing Allocation The commission approved $6.874 million for a pedestrian and bicycle bridge across SR 99 in Sacramento County.
  28. 01:06:22 La Vina Mobility Project Post-Fact Time Extension The commission approved a 12-month post-fact expenditure extension after utility coordination delays and an administrative omission, with commissioners praising corrective measures.
  29. 01:10:33 Ventura County SHOPP Mobility Completion Extension Amendment The commission approved amending the completion period for a Ventura County SHOPP mobility project as an exception to program guidelines.
  30. 01:10:40 Del Norte Bridge Project Expenditure Extension Amendment The commission approved amending the project development expenditure period for a Del Norte County bridge preservation project.
  31. 01:11:23 LA Metro Substation Contract Award Extension Amendment The commission approved six additional months to award LA Metro’s traction power substation replacement contract, extending the deadline to April 30, 2027.
  32. 01:12:42 Active Transportation Project Allocation Extension Amendments The commission approved longer allocation extensions for Nevada County roundabout improvements and Pomona’s San Jose Creek bikeway to address environmental revisions and property negotiations.
  33. 01:13:54 Border to Bayshore Bikeway Completion Extension Amendment The commission approved nine additional months for construction completion, with the chair emphasizing the long-awaited bikeway’s regional importance.

Transcript

Warning: This transcript is automatically generated by machine and may contain errors, including misheard words, misattributed speakers, and omitted passages. Always listen to the audio or video recording before assuming the transcript correctly reflects what was said. Do not rely on the transcript alone for quotation, reporting, or any other purpose where accuracy matters.
Asher we go we shall get started all right thank you for joining us for day two of the
California Transportation Commission hearings in Hanford California we'll we'll start with
roll call Douglas thank you chair commissioner Bradshaw vice chair crude
Mr. Brown Heinz.
Present.
Commissioner Eager.
Present.
Commissioner Grisby.
Present.
Commissioner Gordino.
Present.
Commissioner Mann.
Present.
Commissioner Miller.
Commissioner Fic.
Chair Falcone.
Member Wilson.
We have a quorum.
Thank you Douglas.
And please proceed with.
In two of the October.
For 2026.
CTC meeting in beautiful Hanford.
Home of superior ice cream.
The meeting agenda is located on our website.
beautiful Hanford home of superior ice cream the meeting agenda is located on
our website at www.catc.ca.gov all of the presentations for today's meeting are
also available on the Commission meetings page of our website under the
view download meeting materials tab any document the CTC creates can be
translated into any language you need, simply email us at catcatcatca.gov and we'll have
them return to you as quickly as possible. American Sign Language Translation is being
provided on the webinar for this. You should see the translators on your screen.
Live closed captioning is also available. Please select the show captions tab at the
bottom of your screen. There are a number of language options available there to choose from.
For our presenters, if you're on the agenda to make a presentation, please do your best to be
succinct. Please remember to speak at a steady pace to allow our translating services
for accurate translations. If you are presenting remotely,
we hope that you will turn on your camera assuming you have one.
Likely located on the bottom of the screen. There you will find the raised hand and Q&A tabs.
We encourage you to use the raise hand feature as early into the item as you can
to give the system time to acknowledge you to time to acknowledge excuse me.
Commission staff will let you know when it's your turn to make your comment.
Alternately you may use a Q&A tab to submit your comment in writing.
Please be sure to indicate the agenda item number you are commenting on
and commission staff will read the comment on your behalf.
As a reminder each registered attendee is provided a unique link
and phone number to access the webinar.
these should not be shared with other participants as they are registered to your specific name
and can create confusion for staff when making comments. For all of our meeting attendees, when
you're making your comments please do your best to be concise. Please make sure that your comments
add new information. If you agree with the comments of a previous speaker simply make that statement.
Please remember to speak at a steady pace to allow our translating service adequate time for
accurate translations. Since we often have many speakers we ask that you make your point in two
minutes or less. If for some reason we have many speakers on any single topic
we reserve the right to limit comments to one minute if needed. Thank you for
joining us today. Thank you chair. Thank you Douglas. Alright let's proceed with
78. Airspace Lease Program Update
our agenda item 78 airspace lease program update with Mr. Silverman. Thank
you. Good morning commissioners. Tab 78 is an information item to provide an
update on the Caltrans airspace lease program. In accordance with commissions
resolution for leasing airspace to private entities. Caltrans is required to
submit quarterly reports on the management of its airspace lease program.
These reports keep the Commission informed about Caltrans progress
towards compliance with the resolutions, Caltrans internal guidelines and
procedures, and applicable state and federal laws.
Tierra Moerung, Caltrans headquarters deputy division chief of right-of-way and
land surveys, is here to provide a presentation on the fourth quarter
Airspace Program Report as well as a general update on the Airspace Lease Program.
I'll turn it over to Tiara.
Good morning.
Good morning, Chair Fakoning, Commissioners, and CTC Director.
My name is Tiara Maureen, and I am the Deputy Division Chief for the Division of Ride Away
and Land Surveys.
Thank you for the opportunity to provide an update on the Caltrans Airspace Program for
the fourth quarter of fiscal year 2025-26 which is April 1st, 2026 to June 30th, 2026
and an update of the audit 180 day corrective action and that was submitted to the independent
office of audits and investigations. Next slide please. This presentation will provide
a high level overview of the fourth quarter report for the Caltrans airspace program.
I would like to provide information on the statistics of the program based on sites that are currently being leased
the department currently manages
488 sites which is a decrease from the third quarter in which we manage 506 sites
The uses of sites vary, but I am highlighting for today
Telecommunication wireless which is the highest type of lease in the program at a hundred and sixty seven sites
There are currently a hundred and sixty two sites for parking which may increase over time
Ten are currently being leased for open storage uses all of which are currently being evaluated and there are currently 12 mini storage
facilities within the right away the remaining 137 sites use consists of landscaping and parks
Inspections completed during the first quarter include the fourth quarter include the following that are that were a total of
156 inspections. Four currently have minor issues noted as reviewed by Caltrans staff.
One site had connected extension cords that was cleared during the inspection notice and
its pending clearance. The other two were wireless sites that had unapproved generators
which were removed. Next slide, please. Now we'll take a minute to discuss the open storage
sites within the right-of-way. Per FHWA, open storage is no longer acceptable under interstates.
Headquarters with the assistance of the districts has determined that there are 10 sites in
our inventory that are still considered open storage. This is a reduction from 21 that
we had in quarter one. We continue to work with tenants that have open storage to either
relocate or become compliant with the policies. Next slide. First I would like to define holdovers
as part of our discussion. A holdover occurs when a tenant's lease has expired and there
are currently in a month-to-month tenancy and no additional lease options remain. There
are also no other lease violations that contribute to the holdover. Caltrans continues to holdover
statewide to reduce holdover as part of the resolution g2514 any lease that
requires direct negotiations due to it being landlocked etc require CTC
approval via an agenda item at a commission meeting as we continue to
resolve our holdovers there are many sites statewide that will require
commission approval as we have seen at the previous Commission meetings and we
will continue to see additional requests at future Commission meetings next slide
As shown in the data on the slide, the department currently has 100 holdovers which is down
from 151 that we previously reported in quarter one.
The majority of the holdovers are located in districts four and district seven.
It is expected that the number could continue to increase as leases expire and before our
property is re-cautioned.
Next slide.
The airspace program currently has 23 sites with past due rents of 1.45 million dollars.
Of the 23, there are 11 are wireless with pass-due balances.
1.6 million is pass-due, but we're also carrying a 3.6 million credit balance pass-due that
are received by the Department of State for a wireless site.
In hindsight, adjusting our system to accurately report the pass-due and credit balances.
Holdover and legal actions.
Six are currently pending unlawful detainer actions representing 1.23 million and past
due rent.
The remainder six are currently in negotiation for a repayment plan.
As I have spoken, Caltrans is working diligently to collect all past due rents.
Next slide, please.
All districts submitted a contract for delivery, a CFD, by June 30, 2026.
The review identified 79 sites with compliance issues
such as 59 buildings within the airspace program,
nine mobile buildings, four truck parking sites,
three parking garages, and one tow yard.
Next slide, please.
Over the past year,
the department has achieved many accomplishments.
We have completed several auctions and districts.
We have reduced our statewide inventory
from 506 to 488 sites.
The department will be hosting its first Airspace Academy
in November of 2026, which will provide training
to staff in the airspace program.
Next slide.
Within the fourth quarter we completed a quality,
we completed a quality enhanced joint reviews,
which we refer to as QEJRs.
In addition to the several we had completed in the last year,
we continue to have weekly airspace hot topics meetings
to discuss the fundamentals of the airspace program,
including auctions and direct negotiations.
We continue to partner with the state fire marshal
in addressing concerns and risk
of tenant's usage of the airspace.
The state fire marshal continues to inspect properties
within the state's right-of-way.
Currently, there are 33 state fire marshal inspections
that are considered failure.
This is a decrease from the previous quarter of five.
24 are currently being addressed for tenant corrections.
Six are in LA and are uncorrectable
as there are buildings under structure.
Three are ongoing mini storage inspections
which are inspected in sections.
Next slide, please.
Now we'll brief the commission
on the 180 day corrective action plan
that was provided to the independent office
of audits and investigations.
Recommendation 1.1 required the department
to identify all leases
that have entered into a holdover period
and immediately placed those properties up for auction.
Or if the circumstances and terms are consistent
with the commission's resolution,
directly negotiate a new lease with the respective tenants.
The corrective action was to develop the contract
for delivery and resolve holdovers within 12 months.
The contract for delivery has been completed
and districts are working through the holdovers.
Recommendation 1.2 required the department
to develop a tracking process to notify management
when leases are nearing expiration
and take the necessary steps
to ensure that those properties are subject
to an auction in courts with the law
and the commission's resolution.
The department's corrective action was completed
and districts are being notified
of upcoming expired leases and holdovers.
Next slide.
Recommendation 1.4 required the department
to integrate a management level approval
and justification process,
when district staff decides to directly negotiate
with prospective tenants.
The department's corrective action completed
in a memo was issued to all districts
outlining the process on how to directly negotiate.
There are several parts to completing recommendation 2.1.
The department has completed one of three.
The department is required to send a monthly reminder
of the outstanding internal inspections
for the future two months.
and will include outstanding safety violations,
actions which the department is now doing.
Next slide please.
The department has several other corrective actions
that will be completed within the terms of the commitment
per the corrective action plan.
These include Caltrans will submit a request
to the commission to potentially revise its resolution
to allow for a holdover period.
Headquarters, right away, and CT staff will formally meet
to discuss this option.
Caltrans will be having a formalized air space academy
training in November for current right away agents
within the air space program.
Departments are auditing all records
for escalation accuracy by December 31st, 2026.
Tenants will be notified of billing adjustments
by February 1st, 2027.
Repayment plans must be in place by May 31st, 2027
and fully paid by June 30th, 2028.
The division of right-of-way and land service will continue
to request additional positions in an effort
to right-size the airspace program.
Guidance for districts
on preparing the upcoming lease expirations will be issued
with presentation completion expected by December 31, 2026.
Caltrans will develop annual escalation rates evaluated every
five years based on regional factors
with finalization expected to be by February 1st, 2027,
all future leases will include a flat rate annual escalation clause,
specifying the date and increased rent amounts.
New policy and amend lease templates will be completed by March 1st,
2027. Next slide. Thank you. And I'm open for any questions.
Thank you Tiara. Um, any public comment on the presentation?
No, we did not receive any request from the public to comment on the item.
Thank you, Justin. Any questions or comments from Madias? Commissioner Eger.
Thank you. So just to get my head around this program, so how much money is generated per year
off of these leases? I do not have the answer to that question,
but I can go back and get that answer unless Steven can help me.
So I don't have that number either, but I can tell you this, generally speaking,
is not money that stays with the department. Streets and highways code I think it's 143
specifies that money actually ends up going to pay debt service on transportation bonds so it's
not revenue that we get to use. This airspace lease revenue is not something we get to use.
That was part two of my question. Where does it go after we get it? And do we know what percentage
of the total that we collect is our delinquent.
I do not have the answer to that question either I can go back and take a look at that.
Okay, if you could let me know those, that'd be great. Thank you.
You're welcome. Any other questions? Okay, thank you for outlining a pretty methodical
approach to your corrective actions and hopefully we'll see you know positive
response or outcomes to to the plans that you are that you've laid out and
thank you for for working with our CTC staff as you launch these these
strategies. Quick question. How did you design these corrective actions? Did you, you know,
look at best practices in other markets, other jurisdictions that pretty much do the same thing?
So how did you kind of design this plan? Yes, thank you. Absolutely. So when the auditors
came up and they figured out where they saw that we had some deficiencies. We went back and looked
at our practices and determined how we could remedy those findings. So we looked at our
historical data. We looked at what was working today. We contacted a couple of other states,
specifically like Washington and Oregon and Nevada, to determine how they were working through some of
of those challenges that we were having and after we communicated internally we
decided which items were really reachable attainable and that could work
and that would clear the audit findings. I will add that as we go through these
audit findings we will submit what we have done to the auditor and they
ultimately have the jurisdiction to say yes we agree that you've corrected that
action or no you we do not and we're currently in the review status for the
180 day cap plan right now okay all right well we look forward to hearing
an update as you roll out your corrective action plan and again thank
you for working with us and as particularly our staff as you roll that
out so thank you thank you all right next item airspace lease requests to
79. Airspace Leases: Requests to Directly Negotiate
directly negotiate David commissioners tap 79 is an action item requesting
for Caltrans approval to directly negotiate eight airspace leases. As a
reminder an airspace lease is an agreement that allows public agencies,
private entities, and nonprofit organizations to use space above, below,
or next to the state right away. The Streets and Highways code requires
these leases to be competitively bid unless the Commission finds by unanimous
vote that direct negotiation is in the best interest of the state. Today's
request is the first step. Once negotiations are complete Caltrans will
bring final lease terms back to Commission for approval. So I'll group
these eight leases into two groups. The first group is for six temporary
construction encroachments for private developments next to the state highway.
We can categorize this as five for tower cranes. During construction these crane
arm crane arms will swing over the highway. The six is a tieback lease. It
It allows shoring rods to extend under the highway
while the building's foundations is excavated.
In each of these cases, only the adjacent developer
has use for the space.
There's no competitive use for this kind
of temporary encroachment.
The second group is for leases that are landlocked parcels.
Each parcel can only be reached through an adjacent private
property, so the neighboring owners
are the only practical tenants.
For all eight requests, Caltrans is determined and staff
agreed that direct negotiation isn't the best interest staff recommends approval
Thank You David public comment Justin we do Commissioner man seconded by
Commissioner Grisby all in favor any opposed abstentions okay that item
passes thank you David item 80 has been withdrawn and so we'll move forward to
81. SR 99 and Paige Avenue Supplemental Right-of-Way Funding
item 81 Beverly commissioners tab 81 is a supplemental allocation request of
five million four hundred forty seven thousand dollars in trade corridor
enhancement program funds for the right-of-way phase of the state route 99
corridor and page Avenue multi-modal interchange enhancements project into
Larry County the state route 99 corridor and page Avenue multi-modal interchange
enhancements project was originally programmed in the 2022 trade corridor enhancement program
with $4,552,000 for the right-of-way support phase and $32,417,000 for the right-of-way
capital phase. The project was subsequently programmed with $62,670,000 for the construction
support and capital phases in the 2024 Trade Corridor Enhancement Program, bringing the
total Trade Corridor Enhancement Program funding for the project to $99,639,000.
The State Route 99 corridor and Page Avenue multimodal interchange enhancement project
will add one lane in each direction and the State Route 99 median to improve freight travel
time and reliability and reduce unsafe merging.
The project will also reconstruct the Page Avenue interchange as an under crossing and
add 1.7 miles of class 1 multi-use path and 1.5 miles of sidewalks to improve traffic
flow and protect people walking and biking from heavy duty truck traffic.
The original right of way capital estimate understated the cost of relocating the Tulare
Irrigation District's main canal due to an administrative error.
Additionally, new canal modifications are needed to accommodate Southern California
Edison transmission power lines and maintain traffic on the existing state
Route 99 ramps. To help cover these increased costs, Caltrans and the Tulare
County Association of Governments are requesting $5,447,000 in supplemental
funds for the right-of-way capital phase. In addition to trade corridor
enhancement program supplemental funds. There is an additional $8,172,000 in
local funds being contributed to cover the cost increase. Supplemental trade
corridor enhancement program allocations are drawn from Caltrans's
available cycle 5 trade corridor enhancement program funding capacity.
Staff recommends your approval of this request. Thank you Beverly. Any public
comment. There was no request from the public to comment on the item. Okay. Any
questions, comments, motion from the dais, Commissioner Peter. Thank you. This was a
project that Commissioner Grisby and I went and met with the people in the
neighborhood to look at the improvements that were happening and
certainly this is an extremely important project in that area. I think we toured
it before, and the trucks back up as they're coming off of the freeway to get on to Page
all the way down the freeway and into the neighborhoods. And so when we met with the
neighborhood, you know, they asked for, you know, additional bike lanes and really to
make that multimodal so they could get in and out. And Tulare County has been extremely
flexible in making sure that the needs of the community are being met. So this is right
next to the international ag centers and when the millions of people go in and out, this will
certainly enhance how people get in and out of that area during that time and all year long to
make that safer for the people in the neighborhood. So I know they've been working for many, many,
many, many, many years to get this to the place where they can get it finished and I know we were
very supportive of the neighbors and what they wanted. So I just want to say how important this
was. Thank you. Is that a motion? Yes. I will make a motion. Okay motion from
Commissioner Eager and then the enthusiastic one at that and second by
Commissioner Crisby. Make a comment as well actually. Okay absolutely. I just want to
double down on the fact that this is definitely an environmental justice
community that needed support and going down there I was struck by what they do
do not have. And they're the wealthiest nation on the planet in the history of
humankind. So to extend that bike lane to that community to give them a little
bit better access is the right thing to do, and I'm very enthusiastic that this
is happening. So I'd like more to second that motion. Beautiful, thank you. All in
favor? Aye. Can you pose? Abstentions? Okay, that passes. Thanks, Beverly. Item 82.
Tim. I might be taking 82 through 87. That's correct. Thank you. Tabs 82, 83, 84, 86, 86 and 87. Tim.
Thank you. Yes, as mentioned I will be taking items 82 through 87 with a recommendation at
82. SR 96 Bridge Project Supplemental Environmental Support
the end. Tab 82 is an action item for a shop bridge rehabilitation and replacement project
on State Route 96 in Siskiyou County requesting $300,000 in supplemental funds to complete the
project approval and environmental document phase. Additional funding is
needed due to more extensive hydraulic analysis and revisions to the hydraulic
report. The recommendations from the report required redesign of bridge
abutments and a retaining wall. Funding was also needed to complete a value
analysis study necessary due to the revised total project costs exceeding
83. US 101 Bridge Project Supplemental Construction Support
the threshold requirement to conduct the analysis. Tab 83 is an action item for a
bridge rehabilitation and replacement project on US 101 in Del Norte County
that is requesting 1,200,000 in supplemental funds in construction
support to complete construction. Additional support is needed to
continue efforts related to differing site conditions, additional protection
measures for the mussel population, addressing potential claims, and funding
for inspectors additional inspectors in overtime. Also support costs are needed
to account for delays to temporary bridge removal work and responses to notices of violation
and an enforcement letter from the resource agencies.
84. SR 20 and I-80 Bridge Project Supplemental Construction Support
TAB 84 is a shop bridge formula program project on State Route 20 and Interstate 80 in Nevada
and Placer Counties requesting $2,800,000 in supplemental funds and construction support
to complete construction.
Please note there is an edit to the book item as identified on the change list.
Road construction support is due to differing site conditions, major bridge reconstruction
challenges of the eastbound structure, gaps in the traffic handling and railroad constraints
and flagging, all causing delays that push the project into inclement weather windows.
85. SR 9 Safety Project Supplemental Construction Support
Item 85 is an action item for a shop safety improvements project on State Route 9 in
Santa Cruz County requesting $750,000 in supplemental funds and construction support
complete construction. Additional construction support is needed due to contract change orders
required due to unforeseen utility conflicts, subsurface void added retaining wall and changes
86. SR 216 Rehabilitation Supplemental Construction Funding
to traffic control and drainage work. Item 86 is an action item for a shop roadway rehabilitation
project on State Route 216 in Tulare County that is requesting supplemental funds of $3,574,000
and construction capital, and $1,189,000 in construction support to complete construction.
Additional capital funding is needed to address the discovery of additional unanticipated
underground utilities which required relocations and to install wrought iron fencing under
the bridge and along the retaining wall, to add enhanced lighting to improve visibility
and deter unsafe activities and to place rock blanket around the abutment of the bridge
to prevent structural compromise.
Additional support is needed due to the efforts related to the added scope and due to an increase
in working days due to project delays related to the utility relocations.
87. SR 116 ADA Curb Ramps Supplemental Construction Funding
And item 87 is an action item for a shop ADA curb ramps project on state route 116 in Sonoma
county that is requesting supplemental funds of $1,700,000 in construction capital to close
out the construction contract. The cost increase is due to addressing different site conditions,
restaging construction sequencing, and resolving utility conflicts discovered during construction.
Prior to making my recommendation, I would like to summarize the total cost increases for this
meeting. The total supplemental funds requested at the October CTC meeting is approximately $11
million dollars. I'd like to note that this is the lowest amount requested for
these types of items since June of 2021. The total increase so far for the 26,
27 fiscal year for supplementals and initial allocations greater than 20% of
the program amount is approximately 100 million dollars. Commission staff has
reviewed the projects and book items for items 82 through 87 and recommends
approval. Thank you, Tim and thank you for your perspective. Any public comment, Justin?
There is no request to comment on any of the listed items.
Any questions or comments from the dais? Okay, moved by Commissioner Eger, seconded by
Commissioner Grisby. All in favor? You oppose. Abstentions? Okay, great. Items 82 to 87 passes.
Okay. Moving forward. Item 88, Brandi.
88. SMART Windsor to Healdsburg Supplemental Design Funding
Good morning, commissioners. Tab 88 is an action item to approve supplemental funds
allocations for 800,000 for the PSNE phase of the transit and inner city rail capital
program smart Larksburg to Windsor corridor, the Windsor to Healdsburg component in Sonoma
County. Staff recommends your approval of tab 88. Thanks Brandy. Any public comment?
No there was no requested comment on the item. Thank you. Any questions, comments,
motion from the dice? Moved by Commissioner Mann, seconded by
Commissioner Eger. All in favor? Any opposed? Substantions? Okay that item passes, thank you.
item 89 back to tim thank you and and i i know john usually does these items and so i will do my best
john pray although i won't do it justice you're putting pressure on yourself
89. 2026 SHOPP Amendments
commissioner tab 89 is an action item to approve amendments to the 2026 shop please note there is
one small technical change on the change list with that change this these shop amendments will add
22 new projects and revise 16 projects in the 2026 shop of the 22 new projects 17 of them are
coming from the major damage and safety reservations which leaves five that are not coming from a
reservation. Four are reprogramming previously programmed projects that lapse because Caltrans
didn't deliver the projects within the timely use of funds requirement these projects all four
projects are in Los Angeles County. One project is a new construction manager
general contractor project to install an electronic control system at the
Caldecott tunnels in Alameda County. The project is important to program
now so that it can be implemented along with the tunnel rehabilitation project
that is just starting construction. And then the 16 projects that are being
revised are various proactive changes to scope, cost, and schedule for these
projects staff recommends approval of tab 89 great good job Tim public
comment Justin there was no request to comment on the item okay any questions
comments motion from the dice I'll move and you're no John but you did fine I'll
take it as a compliment he did more than fine okay move by Commissioner eager
seconded by commissioner Mann. All in favor? Any opposed? Abstentions. Okay, that passes.
90. Director’s Orders Annual Close-out Report
Great job. All right, back to you, Tim. Thank you. Tab 90 is an information item
reporting on allocations made by Caltrans for emergency projects in the 25-26 fiscal year.
Please note there's a yellow replacement book item as identified on the change list.
The commission has delegated the authority for Caltrans to allocate funds for emergency projects
in resolution G 2111 which also requires Caltrans to provide an annual report at the completion of
the fiscal year reporting on all allocations made in the prior year. These emergency projects are
mostly most commonly storm damage related but also include wildfire, theft, vandalism and anything
else that threatens our infrastructure or the traveling public and needs to be fixed right away.
At the close of the 25-26 fiscal year, Caltrans approved approximately 801 million in the
construction contracts on 191 projects from the shop Major Damage Reservation.
This year's 801 million is lower than last year's 857 million and significantly lower
than the 1.1 billion and the 1.2 billion we saw two and three years ago.
does get some federal grants and reimbursements to offset some of these
costs through things like FEMA and federal emergency relief funds, but those
grants and reimbursements only cover a fraction of this program's costs and
they may come in future years depending on upon eligibility of the improvements
and availability of federal funds. In fiscal year 25-26 Caltrans received
approximately 248 million in federal emergency relief allocations. As a reminder
this is an information item so no action is required. I would be happy to answer
any questions. Okay, thank you Tim. Any public comment on this item? There was no
request to comment on the item. All right, thank you Justin. Any questions, comments
from the dais. Okay, thank you. Thanks Tim. Item 91 for TSEP, back to Beverly.
91. Trade Corridor Enhancement Program Amendments
Commissioners tab 91 is an amendment to the 2024 trade corridor enhancement
program for two projects. The first project is the Pennsylvania Avenue
grade separation project which was jointly nominated by the city of Beaumont
and Caltrans and programmed with 50 million four hundred thousand dollars
for two components in the 2024 trade corridor enhancement program. Caltrans
and the city are now requesting to withdraw and deprogram the project from
the 2024 program due to outstanding utility coordination, right-of-way
acquisition, and third-party party agreements that create significant risk
in meeting the project's extended allocation deadline. Withdrawal of the
project from the 2024 program will allow Caltrans and the city to address these
issues and resubmit the project for funding consideration in the 2026 trade
quarter enhancement program, the timing of which aligns well with the
projected ready-to-list date. If approved, the removal of this project will reduce
the total funding programmed in the 2024 trade quarter enhancement program by
$50,400,000 and increase the available 2026 trade quarter
enhancement program funding capacity to one billion three hundred thirty eight
million three hundred and fifty eight thousand dollars. The second project is
the Coastal Rail Infrastructure Resiliency Project which was nominated by
the Orange County Transportation Authority and is currently programmed
with eighty million dollars for four components. The Coastal Rail
Infrastructure Resiliency Project proposes track protection activities in
in four areas along a seven-mile segment of the Los Angeles, San Diego, San Luis Obispo
rail corridor, which is also known as the Losan rail corridor. Since 2021, these areas
of the Losan rail corridor have experienced repeated shutdowns due to coastal bluff erosion,
beach and revetment loss, and geologic landslide failures that threaten rail stability, life,
and property. Recent storms have caused additional erosion and slope damage to the project area
area, prompting temporary closures for emergency repairs.
Three project components have already
been allocated and are under construction or complete.
The remaining unallocated component,
called the area four and sand nourishment component,
includes critical sand replenishment work
in three project areas to help protect the rail infrastructure
from damaging storms.
Additionally, the component includes
the construction of an engineered rock revetment
to protect against additional erosion.
Ahead of the predicted El Nino weather event,
the Orange County Transportation Authority
is asking to split these scope elements
into two separate components
to aid in efficient and fast delivery.
Please note that this item has a change on the change list
due to the withdrawal of the related allocation
for this sand replenishment component under tab 100.
The Orange County Transportation Authority
expects to request allocation of both components
an upcoming Commission meeting and they are currently working diligently to
secure the remaining necessary permits. If the Commission approves this
amendment the total trade corridor enhancement program funding program to
the project will remain at 80 million dollars and the full scope will remain
intact. Saff recommends approval of tab 91. Thank you Beverly. Any public comment?
night. Thank you. Thank you.
There was no word. Most of
common on the item. Thank you.
We do have a speaker slip.
Mayor Jessica Voight with the
city of Beaumont. Good
morning, Mayor. Thank you for
being here. Good morning. Thank
you for having us and I must
say that while it's the
morning and I didn't get to
have ice cream this morning, I
did have it yesterday. And it
was delicious. So good morning,
We are both from the city of Beaumont and we absolutely appreciate the opportunity to speak with you today.
The Pennsylvania Avenue grade separation remains one of our top priorities in our city because of its significance in
improving public safety access.
This allows the south side of our city to be accessed during emergencies and without this grade separation
we have an at-grade crossing that
impedes, excuse me, emergency responses during times of emergency.
It will help us to reduce traffic delays, and it does ensure goods move efficiently throughout our region.
This long-term investment is really a complex project that requires more time and careful planning,
and we want to make sure that it delivers the greatest possible benefit to our residents and businesses.
The City's decision to return and reapply for the 2026 funding cycle is a strategic step forward.
This additional time will allow us the opportunity to strengthen the project's readiness,
meet the state requirements and ensure that this project is in the best
possible position to move towards construction. So on behalf of the City
of Boma we are greatly grateful and deeply appreciative of the state's
investment and partnership on this project. We would like to thank the
California Transportation Commission and its staff, especially Beverly, thank you
for all of your help. Riverside County Transit Commission and our partners at
Caltrans for their contributions to this critical infrastructure project
within our community. We respectfully ask for your continued support as we prepare this
project to meet the 2026 funding cycle. The city remains fully committed towards collaborating
with our region, state, and transportation partners to move the Pennsylvania Avenue
grade separation project forward. So thank you for your time. Thank you Mayor. And what I'm finding
in Central Valley is that it is never too early for ice cream. So thank you for sharing how
how transformative this project will be for for the city of Beaumont. Um,
any comments or questions from the dais or motion?
Okay. Um, move, move by, uh,
commissioner Brownhine seconded by a commissioner man. All in favor.
I do have a quick question. Sure. Of course. Sorry,
but not for the mayor is for Beverly. Um,
I was wondering if this is on the state's risk list that we talked about, um,
yesterday because there's a mention of utilities
and railroad negotiations.
I'm wondering if that's on the risk list
that we talked about yesterday.
I do not know the answer to that,
but I can look into it and get back to you, Commissioner.
Right, cool.
Of course, I love this particular project,
and I'm aware of that particular area,
Pennsylvania Avenue, is part of the larger question
I asked yesterday about how those negotiations are doing
broadly speaking around the state because it's a reoccurring issue as everyone knows.
Yeah, so we can get back to you and I can also talk more with the city and RCTC about
the challenges they faced and I can report back to you.
Great. I really appreciate that. Thank you.
Great. We had a motion and a second. Do we vote? Let's vote again. Okay. All in favor.
Any post?
Abstentions?
Okay.
That passes.
Thank you.
Item 92, LaShara.
Good morning commissioners.
92. Windsor US 101 Pedestrian and Bicycle Crossing Programming
Tab 92 is an action item to amend the local partnership formulaic program.
This amendment will add the town of Windsor's downtown pedestrian and bicycle crossing of
US 101 project in Sonoma County and program $1,117,000 in 2024 formulaic funds to the
construction phase in fiscal year 26-27. The project will improve bicycle and
pedestrian safety, accessibility, and connectivity through construction of 0.34 miles of new
pedestrian and bicycle facilities, four enhanced crosswalks, two intersections, and signal
improvements. These improvements will reduce conflicts between vehicles, bicyclists, and
pedestrians, improve accessibility for people of all ages and abilities, and strengthen multimodal
connectivity between the east and west sides of Windsor. This action leaves $65,429,000
of 2024 formulaic program funding available for programming through June 30, 2028. Staff
recommends approval of this item. Thank you, Lashara. Any public comment on this item?
No, there was no request from the public to comment on the item. Okay. Any questions,
or motion from the dais. Moved by commissioner man seconded by second by commissioner grisby
all in favor any stitches no okay that passes thank you lashara joining us virtually is shila
93. Federal Local Assistance Annual Allocation
for item 93 good morning commissioners tab 93 is an action item requesting approval of the
department's annual allocation of federal funds totaling $2,739,885,000 for fiscal year
2026-2027. The department's division of local assistance administers the subvention budget
under the delegated authority from the commission and the request is consistent with the budget act
of 2026. Staff recommends approval of tab 93. Thank you, Sheila. Any public comment?
No, there was no request of comment on the item.
Comments, questions? Motion from the dais.
Moved by Commissioner Eger, seconded by Commissioner Mann. All in favor?
Any abstentions, suppositions? That passes. Thank you. Tabs 94 and 95 will go together.
94. SHOPP Construction Allocations
back to Tim. Thank you commissioners. Tab 95 or I'm sorry 94 is an action item for shop
construction allocations. Please note the change list where one project has been withdrawn and
with that change this item will allocate 110,092,000 for nine shop projects. These nine projects will
improve one bridge, 34 lane miles of pavement, one maintenance station, bridge railing and
complete streets elements, stormwater mitigation projects, and many other
important improvements to help our communities and economy throughout the
95. SHOPP Preconstruction Allocations
state. Tab 95 is an action item for shop
pre-construction allocations. This item will allocate $47,035,000 for 35 shop
pre-construction phases for environmental, design, and right-of-way for projects
throughout the state. Staff recommends approval of TABs 94 and 95. Thank you
Tim. Public comment, Justin? There's no requested comment from the public on
either item. Thank you. Any questions, comments? Motion from the DICE. Move by
Commissioner Eger, seconded by Commissioner Mann. All in favor? Any no
those extensions. Okay those items pass. Thank you Tim. Okay back to Sheila virtually. Thank you.
96. SR 49 San Andreas Southern Gateway Allocation
Commissioners all present tabs 96 and 97 together with the recommendation at the end. Tab 96 and 97 include eight STIP related allocations totaling 5,293,000. These requests include 300,000 for the State Route 49 San Andreas Southern Gateway improvement.
97. Local STIP and Planning Allocations
improvements projects in Gallaveras County and 4,993,000 for a 7 locally administered
STIP in planning, programming, and monitoring allocations.
Collectively, these allocations will support roadway rehabilitation, traffic calming, safety
improvements, and bicycle and pedestrian improvements in Humboldt, Tehama, Sacramento, and Sutter
counties along with regional planning and programming activities in Humboldt,
Lassen, and Butte counties. Staff recommends your approval of tabs 96
and 97. Thank you Sheila. Any public comment? No, there was no requested
comment on either item. Okay. Comments, questions, motion from the dais for items
96 and 97. Moved by Commissioner Eger, seconded by by Commissioner Grisby.
All in favor? Any abstentions? Opposition? Okay those items pass. Local
98. Aten Boulevard Rehabilitation Allocation
partnerships. LaShara. A TAP-98 is an allocation request for $123,000 in local
partnership formulae at program funds for the Eitan Boulevard rehabilitation
project between old State Route 86 and the west right-of-way line of the
Southern Pacific Railroad Project in Imperial County. The rehabilitation
project will improve the roadway surface and add thermoplastic striping. The
project extends the roads useful life by 15 years and is expected to improve
safety for roadway users by increasing visibility for both drivers and non
motorized travelers. Staff recommends your approval of this item. Thank you
LaShara. Any public comment? No there was no requested comment on the item. Okay any
Any questions comments? Motion from the dais. Moved by Commissioner Eger, seconded by Commissioner
Mann. All in favor? Any abstentions? Any opposition? Okay, that item passes. Thank you, Leshara.
99. SMART Healdsburg Extension Allocation
Joining us virtually is Naveen Habib. Good morning, commissioners. TAP99 is an action
item requesting approval of a $162,207,000 allocation from the Solutions for Congested
Corridors program, local partnership, competitive and formulaic programs, and transit and inter-city
rail capital program for the SMART Healdsburg Extension Project in Sonoma County.
The project will extend commuter rail service to Healdsburg, advancing the commission's
strategic goals to move people and goods efficiently.
By reducing congestion on US 101 and expanding multimodal travel options and support a vibrant
economy by improving access to housing, tourism, and economic centers while supporting freight
rail operations.
Staff recommends your approval of tab 99.
Thank you, Naveen.
Any public comment, Justin?
We do have one speaker card, but no requests from any of our virtual attendees.
Okay, thank you.
We have Joanne Parker from SMART.
staff. Thank you. Good morning,
commissioners. I'm here to offer
thanks for your consideration of
this item. And also to give a
brief update on our progress on
the corridor. For those who
don't know, we are the passenger
and short line freight operator
and also building a class one
pathway in our railroad,
publicly owned railroad right
feature to discourage illegal trespass. In the past two years, we've been incredibly productive,
thanks in large part to the state's partnership on our voter approved system. In 2025, we added
an infill station at Petaluma North. I know that some of you were in attendance that are groundbreaking
for that. We also added a new station and a three mile rail extension to the town of Windsor. Again,
thank you for attending and showing your support for our community. We also
opened 10 miles of pathway thanks in part to active transportation program
funds. We're now at 14 stations 48 miles of rail and 39 miles of pathway. We offer
free service for youth and I'm really it's one of the things we're most
excited to report is about 25% of our ridership our kids many traveling to and
from school. We added in 2026 another 19% service thanks in partnership to the
region and our local bus operators. We're now at 48 weekday trips and 24
weekend trips and that 19% service resulted in an additional 23% increase
in ridership. We're happy to report that we carried 1.45 million riders last year
and decreased vehicle miles traveled by 32.5 million miles. We've also had 1.3
million trips on our pathway. This investment thanks thanks to your team
working through this with us it has not been easy it's taken a lot of time and a
lot of a lot of people in the Zoom room and we're grateful because we're
delivering this project with a relatively new method progressive
design build. We are anticipating with your approval today is it as expired to
award a contract on Wednesday and we look forward to celebrating the
to work with you. Thank you and
thank you for the progress of
the extension with you when it's
completed. Thank you. Thank you,
Joanne. It's nice to see you
again. Um okay. We have a
comment from Commissioner
Grisby. Thank you, Chair. Um,
just wanted to provide my
accolade for this project and
for all the work being done
along the corridor. I got a
chance to go to a lot of those
how excited people are in the community for these projects.
And also the great work being done to connect bike
and ped connections to the stations,
as well as enhance zoning around the stations as well.
So as I said on the ground,
there you all are doing everything right.
And I want to move this item
and thank you for the great work you're doing.
Fantastic.
Okay, motion made by Commissioner Grisby.
Commissioner Eager, yeah.
I just wanted to thank Naveen.
Sorry, you're not here, Naveen, we miss you.
And congratulate your team on working so closely
on these projects.
I know how important that is
for everybody to be working together.
And congratulations to you for all the work
that you've done up until now, and I will second.
Great, okay.
We have a motion and seconded by Commissioner Eger,
and I think we have a comment by Commissioner Mann.
Thank you.
I just wanted to thank you for sharing this project,
but also lifting up the information
related to your youth writership and how many of them
are taking it and then that no charge service for them.
So thank you for that information.
I mean, those are the future stewards of the system.
So thank you for highlighting it.
All right, we have a motion and a second.
And just a quick comment is I did have the opportunity
last May, as you know, to attend the,
guess you call it a groundbreaking or or it was it was a stake at Healdsburg
and I was very struck by the support huge support by the community very
excited about what what the rail means to all of the region not just Healdsburg
and so and how you're cultivating future ridership especially for you is very
impressive. So thank you for sharing that perspective and what you're all
doing to really encourage ridership. So with that we have a motion and a second
all in favor? Aye. Any abstentions? Any no's? Okay that passes. Thank you. Thank you
Navin. Okay we are going to jump ahead a little bit and we'll come back to items
items 1 to 1 to 105. We will proceed with item 106 and we do have a recusal from Commissioner
Mann.
Thank you. I'm going to recuse myself from this item out of the abundance of caution
due to a potential financial conflict.
Thank you.
Thank you for that.
Commissioner Mann, why don't you go wait at the ice cream place? We'll meet you there.
to be on the phone. Okay?
Can you bring us some please?
They don't open till 11. We
already checked out there. Okay.
I thought they had ice cream
for breakfast. Need to make
that happen. You can eat
breakfast at 11. They do. Okay.
All right. Brandi. Go ahead.
106. Transit and Intercity Rail Capital Program Allocations
Thank you, commissioners. Uh
tab one Oh, six and is it an
transit and inner city rail capital program funds for 11 projects in various counties.
And I will quickly shout out, I did see Madera and Fresno and Tulare in our list today.
So these projects expand and improve California's inner city, commuter and urban rail systems,
and the bus and ferry transit systems, including integration with the high speed rail system,
increasing ridership improving safety and significantly reducing emissions of greenhouse
gases vehicle miles traveled and congestion staff recommend your approval of tab 106 thank you
brandy any public comment nobody did not receive any request to comment on the item okay um any
questions comments motion from the dais moved by commissioner eager seconded by second by
Commissioner Grisby. All in favor? Any opposed? Abstentions? Okay, that path.
Madam Chair, if we could just acknowledge on the record that Commissioner Tiffany has joined us
briefly. Thank you. And thank you, Commissioner Tiffany, for joining us on this item. Let's go
back to tabs 101 to 103, and joining us virtually is Kenneth Lopez. Madam Chair, if we could
acknowledge tab 100 has been withdrawn. Ah yes thank you. Item 100 has been withdrawn.
So moving forward to items 101, 102 and 103. Good morning commissioners. Earl present tabs 101
101. Hueneme Road Widening Allocation
through 103 together with our recommendation at the end. Tab 101 is an allocation request of 15
million 84 thousand dollars for plans specifications and estimates and right away faces of the local
administered multi-funded state transportation improvement program and trade corridor enhancement
program. Waineme Road Wainen, Edison Drive to Rice Avenue project in Ventura County. The project
will provide bottleneck relief, reduce congestion, increase freight throughput, and improve safety on
102. Long Beach–East Los Angeles Zero-Emissions Truck Allocation
a facility serving the Port of Waineme in a U.S. Naval base. Top 102 is an allocation request of
three million six hundred and fifty three thousand dollars for the locally ministered
trade corridor enhancement program Long Beach is Los Angeles corridor zero emissions emanate energy
truck project in Los Angeles county. The project will address needed infrastructure to support
the transition to zero emission heavy duty trucks along I-710 a priority clean freight corridor.
103. EV Realty South Bay Truck Charging Hub Allocation
TAB 103 is an allocation request of $7,900,000 for the state-administered
trade corridor enhancement program, EV realty, South Bay Truck Charging Hub project in Los
Angeles County. This zero-emission heavy-duty vehicle charging project will support the
transition to zero-emission freight, helping California achieve its climate goals.
staff recommends your approval of fabs 101, 102, and 103. Thank you Kenneth. Public comment,
Justin. There was no request to comment from the public on either or any of the listed items.
Okay, back at the dais. Any questions, comments, motion from the dais?
Moved by Commissioner Eger, seconded by by Commissioner Mann. All in favor? Any noes,
Substantians. Okay, items 101, 102, and 103 passes. Tabs 104 and 105 together.
Rebecca joining us virtually. Thank you and good morning Chair Falcon and Commissioners.
Tabs 104 and 105 will be presented together with a recommendation at the end.
104. Local Active Transportation Program Allocations
TAB 104 requests allocation of $12,341,000 in active transportation program funds
for seven projects in various counties off the state highway system. Please note that projects
four and seven have been pulled as reflected on the change list. Three of these projects request
allocations for their respective construction phases which will prioritize safety for those
walking, biking, and rolling by collectively installing 4200 feet of new bicycle lanes,
16,000 feet of paved pathways, 56 curb ramps, and improving pedestrian visibility
at crossing facilities through improved lighting and the installation of designated crosswalks
105. Laguna Creek Trail Crossing Allocation
and crossing beacons. Tab 105 requests allocation of $6,874,000 for the locally administered
Laguna Creek inter-regional trail crossing at State Route 99 project on the State Highway
System in Sacramento County. This project will enhance accessibility and connectivity
to support a healthier environment for all by constructing a pedestrian and bicycle bridge
across State Route 99. Staff recommends your approval of tabs 104 and 105.
Thank you Rebecca. Public comment Justin.
Would not receive any requests from the public to comment on either these items. Okay. Thank you
Any comments questions motion from the dice?
moved by commissioner man seconded by
Commissioner brown heights, um all in favor
Any no abstentions, okay
those items pass
moving on to time extensions, um tabs
seven to 117. These are action items consisting of time extension requests for projects from the
following programs. State highway operation and protection program, state transportation
improvement program, local partnership program, active transportation program, and transit and
intercity rail capital program. Staff has reviewed these requests and determined they are consistent
with the respective program guidelines. Staff recommends your approval of tabs 107 through 117.
Thank you Justin. Any public comment Justin?
There's no request to comment on any of the listed items by Justin.
Okay thank you. Any questions, comments, motion from the dais?
Okay. Yes, move by Commissioner Eater, second by Commissioner Grisby. All in favor?
Aye. Any opposed? Abstentions? Okay those items pass. Moving on to post fact time extensions item
118. La Vina Mobility Project Post-Fact Time Extension
118 back to Rebecca. Thank you Chair Kalkin. Commissioners tab 118 is an action item to
consider approval of requests for a 12-month post-fact time extension for the period of
project development expenditure, for the plans, specifications and estimate and right-of-way phases
for the LaVena Community Mobility and Safety Enhancements Project. This time extension request
is an exception to the Active Transportation Program guidelines. The implementing agency,
Madera County requested additional time to account for delays due to extended coordination
with Pacific Gas and Electric. This is a post-fact request because the request was inadvertently not
moved forward to headquarters so that it could be added to the May 2026 Commission Agenda.
The district has committed to training staff on deadlines so this does not happen again.
Staff has reviewed this request and recommends approval.
Thank you, Rebecca. Any public comment? We have a comment by Commissioner Eater. Yes, thank you,
and I just want to thank staff and Caltrans for working together to move this forward. This is a
low-income community. This is certainly something that was extremely needed, and I know that
Madera County put this in early, and I just want to say how refreshing it was, that when I asked
Caltrans District 6. What happened here? How did this slip through? They fessed up. They ate it
and said we are so sorry. We didn't notice it. It slipped through the cracks, but here's all
the things that we have put in place to make sure that it can never happen again and that we're
following the guidelines of Sacramento in ensuring that back and forth everybody does the checks and
double checks and I just want to say I really appreciate the the honesty and
the teams working together to make sure that these kinds of projects that really
need to go through get through so thank you Caltrans thank you Madera thank you
to District 6 specifically for ensuring that this goes through and thank you to
the CTC staff for understanding that sometimes these kinds of things happen
but we're not gonna let it happen again.
So with that, I will make a motion.
All right, motion by Commissioner Eager
and there's always opportunities for lessons learned.
Yeah.
So well done.
And that's for you Bob.
Lessons learned.
That's for Bob, yes.
And I hear a second by Commissioner Eager
for conversation and vulnerability
and ability to learn as you move forward.
And I think that speaks so highly of the community
But then also the interaction with the CTC staff
to be able to have those open conversations.
Thank you.
Working in government for many, many, many, many years.
I absolutely agree with the both of you.
So thank you for those comments.
And hopefully we continue to see that kind of open communication
between the community and our agencies and our staff.
It's just good government.
So with that, all in favor.
Aye.
Any no's, abstentions?
OK.
That item passes.
Thank you, Rebecca.
Hang tight.
I think you're closing us off at the end of this hearing.
So tabs 119 to 120, Justin.
Tabs 119 and tab 120 are action items
for your consideration regarding the approval of time extension
amendments as exceptions to the SHOP guidelines.
119. Ventura County SHOPP Mobility Completion Extension Amendment
TAB 119 is an amendment to the project completion period
for one SHOP mobility project in Ventura County.
120. Del Norte Bridge Project Expenditure Extension Amendment
TAB 120 is an amendment to the project development expenditure
period for one SHOP bridge preservation
project in Del Norte County.
Commission staff has reviewed these requests
and recommends approval of TAB 119 and 120.
Thank you, Justin.
Justin Hall, any public comment?
No, there was no request to comment on either item.
Thank you.
Any comments, questions, motion from the dais?
Moved by Commissioner Grisby,
seconded by Commissioner Eger.
All in favor?
No, abstentions.
Okay, those items pass.
Thank you, Justin.
Back virtually to Naveen.
Thank you, Chair.
121. LA Metro Substation Contract Award Extension Amendment
Tab 121 is an action item requesting approval
an amendment to the contract award time extension for LA Metro's 20 million dollar core capacity and
system integration project component in Los Angeles County. The project will replace four
traction power substations along LA Metro's C and K light rail lines. Due to increased project costs
identified during the bid evaluation process and additional time needed to secure local funding
and complete contract approvals, LA Metro is requesting an additional six months,
extending the contract award deadline to April 30th, 2027. Staff recommends your approval of tab 121.
Thank you, Naveen. Justin, any public comment on this item?
No, there was no request to comment on the item.
Okay, any questions, comments? Motion from the dais? Commissioner Mann? Okay, moved by
I'm sorry. I'm sorry. Commissioner Man seconded by
Commissioner Grisby on favor. Any nose. Abstentions Okay, that
items pass. Thank you. Naveen. Uh, tabs 22 and 23 back to
Rebecca. Thanks again, Commissioner. Um, tabs 122 and 123
again will be presented together with the recommendation at the
122. Active Transportation Project Allocation Extension Amendments
end. Tab. 122 is an action item to consider amending the
for the State Route 174 slash 49 slash 20 roundabout and active transportation safety project in
Nevada County, which requests that its 15-month allocation time extension for the PSNE and right
of way phases be amended to 20 total months. This additional time will allow the project team to
complete environmental document revisions relating to design changes driven by city council and
and stakeholder feedback. The implementing agency has covered the expenses incurred for
these tasks since the June 30th, 2026 expenditure deadline for the phase has passed. The San
Jose Creek multi-use bikeway in the city of Pomona in Los Angeles County requests that
its 16-month allocation time extension for the PS&E and right-of-way phases be amended
to 20 months. This extra time will allow the city to complete negotiations with property owners
and obtain right-of-way certification which is anticipated for February 2027.
123. Border to Bayshore Bikeway Completion Extension Amendment
Tab 123 is an action item to consider amending the project completion period for the for the
following project in San Diego County off the state highway system. The regional border to bikeway,
sorry, their regional border to Bayshore Bikeway project in San Diego.
Try saying that very fast, many times.
A lot of bees request that nine months be added to its original
12-month project completion time extension for the construction phase.
The project, which involves multi-jurisdictional stakeholders,
has secured funding to implement safety and operational improvements
in response to concerns raised by partner agencies
and seeks this additional time to complete their project.
Staff recommends your approval of tabs 122 and 123
Thank You Rebecca any public comment Justin nobody not receive any request to comment on either item
All right any comments questions motion from the dais
Okay, thank you for all your work on the
specifically on the
Border to Bay Shore bikeway project. I know it's a time extension
this is a project that
We in the region are very eager for for this to
To be completed. This is
multi-jurisdictions as Rebecca mentioned
including a connection to the border, so
We have been waiting a very long time for decades really for this
25 to I don't know it's it's it's probably close to 30 mile
bikeway a
system in southern part of
San Diego region. And so appreciate everyone's work to really focus on completing this really
important bikeway corridor. With that, do I hear a motion? Okay, motion by Commissioner Mann,
seconded by by Commissioner Eger. All in favor? Any opposed? Abstentions? Okay, thank you.
back to Justin for any public comment not on the agenda thank you chair we do have one virtual
attendee with her hand raised at this time I'd like to call on Kelly Brinkman hello can you hear
me yes we can okay hi my name is Kelly Brinkman and I'm speaking today on behalf of the United
Caltrans tenants of the 710 corridor I'm also a Pasadena resident who has lived in the Caltrans
own home for 20 years. For Caltrans tenants this process has become a frustrating cycle of hurry
up and wait. We have been urged to prepare to purchase our homes, submit financial documents,
and meet deadlines. Now that AB 2329 has passed, we are once again waiting for regulations that will
determine our future. Meanwhile, tenants remain in limbo. Uncertain about their homes, whether they
they will receive a fair opportunity to become homeowners,
we are asking Caltrans Transportation Commission
to take a meaningful action.
First, every tenant must have a fair opportunity
to purchase their homes.
This must include residents of multifamily properties
and tenants pursuing affordable housing options.
No tenant should be unfairly excluded
because of property classifications
or the purchase pathway available to them.
Second, we are we ask for a fair and transparent valuation process. We want the 2009-19 valuation
used as a reference point adjusted to reflect each property its actual condition as is faces
consistent with AB-23 and its implementing regulations. Years of deferred maintenance and
and necessary repairs must be considered.
Tenants should not be expected to pay a price
that ignores the actual condition of their homes.
Third, we ask the commission to be specific actions.
Please request a public status report from Caltrans,
establish a clear timeline for implementing
the regulations and require written clarification
of eligibility, valuation, and purchase procedure.
We also ask meaningful opportunities to,
for tenants to provide input and for regular public updates
until this process is completed.
Thank you for your time.
Did I, do I have, do I have more time or am I?
No, you have time for your time.
Thank you, Ms. Prinkman.
Okay, thank you so much.
Any other comments, Justin?
We did not receive any other requests
to comment at this time.
Okay, great.
Back at the dais for any closing comments
from commissioners yes mr. Kett sorry not a commissioner but I did want to go
back and correct a statement that I made on tab 78 commissioner eager you were
asking about revenue I cited the wrong streets and highways code so for the
record it's section 183.1 of the streets and highways code that sends that
miscellaneous revenue is what it's formally called to the transportation
debt service fund thank you for that clarification Stephen we had all caught
that. It's come up before so I just wanted to make sure I got it right. Thank you. Just covering
your bases, yes. Thank you, Stephen. Any other comments from commissioners, Commissioner Eger,
of course. Oh, I just wanted to thank the folks here in King's County for a lovely three days.
Thank you for the weather. That was perfect. Yeah.
And we look forward to going to Palm Desert. Is it Palm Desert or going?
Palm Desert. Douglas. Next, and we're hoping to see you all there, but this has
really been a very enlightening and pleasant three days here in beautiful
Kings County and don't stop believing. You're here. Any other comments from
commissioners? I too want to just thank Kings County and the city of of Hanford
and all the communities surrounding Hanford and for those who traveled to
be here. This has been a very productive and actually a really warm and inviting hearing
and wanted to extend my appreciation to Commissioner Eager for pretty much acting as a co-host
here and helping wrangle and organize folks so that we can have this hearing in this very
lovely and beautiful community and I have to say it's been a very productive
last few days totaling at three point four billion dollars equating to total
of thirty seven thousand five hundred and one jobs well done everyone and you
know just the comments coming from the speakers and our staff particularly in
our engineering team, you know, paying compliments to the work that's being done collaboratively
between the agencies. Let's keep that up. I know there's a lot of conversations that
happen behind the scenes to get us to these hearings where it relatively runs very smoothly,
It's a lot of staff at the CTC and Caltrans and our partnering agencies throughout the region
and our local agencies. Thank you!